I attended a very interesting City Council Work Session Thursday to discuss City Dock and Carr’s Beach. Here are the updates:

City Dock

Schedule:

Phase 1A: April-Oct, 2025 (ongoing, complete to clear for boat shows)

• Harbormaster Bldg

• Utility & Electric Work

Phase 1: Nov 2025-March 2027

• Welcome Center

• Craig Street -Susan Campbell Park

• Prince George St. Park Elevation

Phase 2: Nov 2026-Oct 2027

• Craig St – Market House

• Around to Choptank Restaurant

Total project cost is $86M

Federal Grants: $37.34M including $33M FEMA grant

• State: $10M

• City: $37M

• County: $2M

• Plus working on Private Donations: $1M

FEMA Grant:

• Annapolis Director of Public Works is confident city will get FEMA grant

• Should hear end of August

• If we don’t get grant, project will go forward but downscaled; it would take 12 to 18 months to create new plan

Carr’s Beach

• Project includes beach with lifeguard, ferry landing/fishing dock, kayak launch, social gathering space, cabanas, pavilion, grove, welcome center, and interpretive signage

• Project is fully funded

• Project will go to bid when permitting process is completed; contractor will be identified in 1 to 2 months and then construction is expected to take 4 months

• Anticipate completion in 2026

ree
ree

 
 
Frank Thorp for Ward 8 Alderman Logo - "A voice for Ward 8"
  • Facebook
  • Instagram

Frank Thorp was a Rear Admiral in the U.S. Navy. Use of his military rank, job titles, and photographs in uniform does not imply endorsement by the Department of the Navy or the Department of Defense.

Please make checks payable to Friends of Frank Thorp and mail to PO Box 3045, Annapolis, MD 21403

CONTACT US

DONATE

BY AUTHORITY: FRIENDS OF FRANK THORP, FRIEDA K. WILDEY, TREASURER

bottom of page